占支配地位的能源 在弗吉尼亚的离岸风力项目, 完成50%, 面临成本上升 和鲸鱼保护诉讼。 Dominion Energy's Virginia offshore wind project, 50% complete, faces cost increases and a whale protection lawsuit.
位于维吉尼亚海滩外的2.6个GW风力农场, 50%已完成, 并正在2026年完成。 Dominion Energy's Coastal Virginia Offshore Wind project, a 2.6 GW wind farm off Virginia Beach, is 50% complete and on track for 2026 completion. 它创造了2 000个工作岗位,创造了20亿美元的经济活动。 It has created 2,000 jobs and generated $2 billion in economic activity. 由于网络和岸上电力互联费用较高,费用从98亿美元增至107亿美元。 Costs have risen from $9.8 billion to $10.7 billion due to higher network and onshore electrical interconnection costs. 该项目预计将为多达66万户家庭供电,并面临有关北美右鲸种群问题的诉讼。 The project is expected to power up to 660,000 homes and faces a lawsuit over concerns about the North American right whale population.