马萨诸塞州最高法院批准了Eversource在东波士顿的电力变电站建设, Massachusetts Supreme Judicial Court approves Eversource's electric substation construction in East Boston despite resistance.
马萨诸塞州最高司法法院批准EverSource在东波士顿建造电站, The Massachusetts Supreme Judicial Court has approved Eversource's construction of an electric substation in East Boston, despite significant opposition from residents and environmental activists. 批评者认为,该地点构成洪水风险,并受到污染。 Critics argue the site poses flood risks and is contaminated. 项目在2023年1月开始建设,此前有84%的选民反对该项目. Construction began in January 2023, following a non-binding ballot where 84% of voters opposed the project. 在持续的法律挑战中,Eversource 致力于在未来项目中加强社区参与。 Eversource commits to enhancing community engagement in future projects amid ongoing legal challenges.