Mediation failed in a dispute between Lonadale Ltd and the Irish government over halted refugee housing plans in Dublin.
伦达尔有限公司与爱尔兰政府之间关于将都柏林两办公楼改造为难民住宿的计划的法律纠纷中,调解失败.
Mediation has failed in a legal dispute between Lonadale Ltd and the Irish Government over plans to convert two Dublin office buildings into refugee accommodation.
伦达尔声称,根据政府的协议在2025年2月花费了600万欧元进行翻新,以每天90欧元为158人提供住宿,计划于夏季开始.
Lonadale claims it spent €6 million on renovations based on government agreements in February 2025 to house 158 people at €90 per day, with a planned summer start.
由于难民安置的责任被转移到司法部,该项目于2025年7月停止.
The project was halted in July 2025 after refugee accommodation responsibilities were transferred to the Department of Justice.
伦达尔起诉政府部长,指控他们违反合同,虚假陈述和非法干涉.
Lonadale sued government ministers, alleging breach of contract, misrepresentation, and unlawful interference.
法院敦促进一步努力解决此事.
The case was adjourned to October, with the court urging further efforts to resolve the matter.