Victoria’s myki upgrade is delayed until 2028, over budget, and facing criticism over its cost and benefits.
根据维多利亚州审计总监的报告, 维多尼亚省28亿美元的myki票房升级计划落后18个月,
Victoria’s $2.8 billion myki ticketing upgrade is 18 months behind schedule and $136 million over budget, according to a Victorian Auditor-General’s report.
项目旨在引入按键付款和基于账户的票务,但由于不切实际的时间表,未解决的合同问题以及缺乏适当的福利计划而面临延误.
The project, aimed at introducing tap-and-go payments and account-based ticketing, faced delays due to unrealistic timelines, unresolved contract issues, and lack of a proper benefit plan.
新系统的试验已经在部分线路上开始,但预计到2028年中期将全面推出.
A trial of the new system has begun on select lines, but full rollout is now expected by mid-2028.
政府表示, 升级将改善通道和减少欺诈行为, 但审计师质疑其价值,
The government says the upgrade will improve access and reduce fraud, though the auditor questioned its value given low existing fare evasion rates.
由于政策变化, 包括18岁以下的免费旅行.
Work paused due to policy changes, including free travel for under-18s.