卡纳维拉尔港13层停车场开始修建,以增加游轮进出,预定2026年秋季竣工。
Port Canaveral starts 13-story parking garage to boost cruise access, with completion set for fall 2026.
卡纳维拉尔港已开始在6号游轮航站楼的13层9 300万美元的停车场进行垂直建筑,增加了3 732个车位,并将港口总容量扩大到近17 500个。
Port Canaveral has begun vertical construction on a 13-story, $93 million parking garage at Cruise Terminal 6, adding 3,732 spaces and expanding the port’s total capacity to nearly 17,500.
该项目是近10亿美元的基本建设改进方案的一部分,包括8部电梯、车辆坡道和连接邻近车库和终端的桥梁。
The project, part of a nearly $1 billion capital improvement program, includes eight elevators, vehicle ramps, and bridges connecting to adjacent garages and terminals.
计划到2026年秋季竣工,其目的是增加该港口75%的乘车前往游轮旅客的进出通道,并支持其作为国家最繁忙游轮港口的地位。
Scheduled for completion by fall 2026, it aims to enhance access for the port’s 75% drive-to cruise passengers and support its status as the nation’s busiest cruise port.