Tamworth摊位的 Greyhound赛跑计划, 由于错过了最后期限, 推迟了6 - 12个月的项目。
Greyhound racing plans in Tamworth stall due to missed deadlines, delaying project by 6–12 months.
澳大利亚塔姆沃思新赛狗场地的计划因新南威尔士灰狗赛马队错过了在伯格曼斯巷获得场地的关键截止日期而陷入停滞,促使新南威尔士州马车赛车队撤销了该协议。
Plans for a new greyhound racing facility in Tamworth, Australia, have stalled after Greyhound Racing NSW missed key deadlines to secure a site on Burgmanns Lane, prompting Harness Racing NSW to rescind the agreement.
由于未满足开发应用要求而造成的延误,使项目推迟了6至12个月。
The delay, stemming from unmet development application requirements, has set the project back six to 12 months.
GRNSW继续致力于建造一条新轨道,目标是在2026年底或2027年初开工,而Tamworth Greyhound赛马俱乐部则准备出售其Showground路的家。
GRNSW remains committed to building a new track, aiming to start construction by late 2026 or early 2027, while the Tamworth Greyhound Racing Club prepares to sell its Showground Road home.