Hombre Muerto West阶段1接近完成,第一批锂装运预计为H2 2026。
Hombre Muerto West Phase 1 nears completion, with first lithium shipments expected in H2 2026.
Hombre Muerto West 阶段1的建造工程已完成92%,测试和试运行将很快开始。
Hombre Muerto West Phase 1 construction is 92% complete, with testing and commissioning set to begin soon.
纳米过滤厂正在现场组装,由25名以上人员支持,在悉尼进行预先测试。
The nanofiltration plant is being assembled on-site, supported by over 25 personnel and pre-testing in Sydney.
Galan Lithium已积累了庞大的盐水库存,能够快速转向加工。
Galan Lithium has built a large brine inventory, enabling a quick shift to processing.
预计第一批经过加工的盐水将在2026年年初处理,氯化锂浓缩液用于H1 2026,第一批装运用于H2 2026。
First processed brine is expected in early Q2 2026, with lithium chloride concentrate targeted for H1 2026 and the first shipment in H2 2026.
该厂设计了5 200多吨碳酸锂当量,可扩大至21 000吨,并可能扩大至60 000吨。
The plant, designed for over 5,200 tpa lithium carbonate equivalent, could expand to 21,000 tpa and potentially 60,000 tpa.
该项目受益于阿根廷的RIGI投资框架,并且是全球成本最低的锂生产国之一。
The project benefits from Argentina’s RIGI investment framework and is among the lowest-cost lithium producers globally.