Wollongong的Crownview公寓项目仍然处于停工令第三次延期之下,原因是正在进行的未经授权的建筑工程,允许的安全工作有限,买方退款。
The Crownview Apartments project in Wollongong remains under a third extension of its Stop Work Order due to ongoing unauthorized construction, with limited safety work allowed and buyers refunded.
Wolloongong医院附近的Crownview公寓项目由于正在进行的未经授权的建筑工程,被新南威尔士州建筑委员会发布的停工令第三次延长。
The Crownview Apartments project near Wollongong Hospital has been under a third extension of its Stop Work Order, issued by NSW Building Commission due to ongoing unauthorized construction.
这项命令于2024年2月首次执行,于2025年延长,并于2026年2月再次延长,因为检查发现,尽管有禁令,但工作仍在继续。
The order, first imposed in February 2024, was renewed in 2025 and again in February 2026 after inspections found work continued despite prohibitions.
该网站仍然处于禁止令和建筑工程校正令之下。
The site remains under a Prohibition Order and a Building Works Rectification Order.
延长可以进行有限的安全相关工作,包括消防系统升级,而开发商则安排合格的建筑商完成补救工作。
The extension allows limited safety-related work, including fire system upgrades, while the developer arranges for a qualified builder to complete remedial work.
据报告,在前建筑专员David Chandler的干预下,所有购买者都退还了存款。
All buyers have reportedly had deposits refunded following intervention by former Building Commissioner David Chandler.
复杂的工程解决方案可望确保结构安全,但随着官员继续协调补救计划,项目的未来仍不确定。
A complex engineering solution is expected to ensure structural safety, but the project’s future remains uncertain as officials continue coordinating on remediation plans.