科罗拉多州引入了HB 1226来管理成本和排放,因为联邦命令延长了克雷格电站煤厂的运营。
Colorado introduces HB 1226 to manage costs and emissions after federal order extends Craig Station coal plant operation.
科罗拉多州立法者正在推出HB 1226, 以回应联邦紧急命令, 以西方能源短缺为由,
Colorado lawmakers are introducing HB 1226 to respond to a federal emergency order keeping the Craig Station Unit 1 coal plant open past its 2025 closure date, citing energy shortages in the West.
该法案旨在保护消费者,允许低息国家支持的债券支付费用,授权每季度就费用和产出提交公开报告,并对超过排放阈值的工厂实行更严格的污染限制。
The bill aims to protect consumers by allowing low-interest state-backed bonds to cover costs, mandating quarterly public reports on expenses and output, and imposing stricter pollution limits on plants that exceed emission thresholds.
在公用事业、环境团体和州总检察长的推后,联邦指令提出了不公平的财政负担,破坏了清洁能源的目标。
It follows pushback from utilities, environmental groups, and the state attorney general, who argue the federal directive imposes unfair financial burdens and undermines clean energy goals.