MACH能源公司力求在新的气候审查规则下,扩大和扩展其山区热煤矿。
MACH Energy seeks to extend and expand its Mount Pleasant coal mine amid new climate review rules.
澳大利亚能源部已请求将其 " 山平板煤矿 " 作业延长6年,至2032年12月31日,并在2024年法院推翻了事先扩大许可的裁决后,将煤炭开采量增至每年1 250万吨。
MACH Energy Australia has requested a six-year extension of its Mount Pleasant coal mine operations until December 31, 2032, and an increase in coal extraction to 12.5 million tonnes per year, following a 2024 court ruling that overturned a prior expansion approval.
该决定由社区团体DAMS HEG赢得,要求在上亨特地区所有矿物燃料项目批准时评估气候变化的影响。
The decision, won by community group DAMS HEG, requires climate change impacts to be assessed in all fossil fuel project approvals in the Upper Hunter region.
目前的矿山许可证将于2026年12月22日到期,
The current mine permit expires December 22, 2026, and MACH is preparing a modification report for submission.