阿塞拜疆开始建造一条330千瓦的电线,将纳希切万与其电网和欧洲连接起来。
Azerbaijan starts building a 330-kV power line to connect Nakhchivan to its grid and Europe.
阿塞拜疆已开始建造Zangezur电线,这是一个将纳希切万自治共和国与全国电网和更广泛的阿塞拜疆-土耳其-欧洲能源走廊连接起来的330千伏输电项目。
Azerbaijan has begun construction of the Zangezur power line, a 330-kilovolt transmission project linking the Nakhchivan Autonomous Republic to the national grid and the broader Azerbaijan-Turkey-Europe energy corridor.
这条线路穿过崎岖的地形,横跨179公里,在纳希切万新建了一个330千伏变电站。
The line spans 179 kilometers through rugged terrain, with a new 330-kV substation being built in Nakhchivan.
未来阶段包括44公里延伸至Zangezur走廊和一条230公里400千伏的通往土耳其的线路,以及阿塞拜疆的第一个400千伏转换器分站。
Future phases include a 44-kilometer extension through the Zangezur corridor and a 230-kilometer 400-kV line to Turkey, along with Azerbaijan’s first 400-kV converter substation.
该项目旨在将Nakhchivan纳入国家能源系统,结束对外国频率管制的依赖,并促成向欧洲出口电力。
The project aims to integrate Nakhchivan into the national energy system, end reliance on foreign frequency regulation, and enable electricity exports to Europe.
它被认为是阿塞拜疆最重要的能源倡议之一。
It is considered one of Azerbaijan’s most significant energy initiatives.