阿塞拜疆巴库造船厂的三艘新油轮已完工35%至40%,用于石油和化学运输。
Three new tankers at Azerbaijan’s Baku Shipyard are 35% to 40% complete, built for oil and chemical transport.
在阿塞拜疆巴库造船厂建造三艘新油轮的工程已完成35%至40%,一艘船舶完成40%,两艘完成35%。
Construction on three new tankers at Azerbaijan’s Baku Shipyard is 35% to 40% complete, with one vessel at 40% and two at 35% completion.
这艘141米长的船舶,为7 740吨的重量和10海里的最高速度建造,是为浅港口设计的,符合国际安全和环境标准。
Built for a deadweight of 7,740 tons and a top speed of 10 knots, the 141-meter-long ships are designed for shallow ports and meet international safety and environmental standards.
该项目由ASCO在AZCON控股公司下订购,遵循了Akademik Khoshbakht Yusifzade和Zangilan等以前交付的油轮的设计。
The project, ordered by ASCO under AZCON Holding, follows the design of previously delivered tankers like Akademik Khoshbakht Yusifzade and Zangilan.
巴库造船厂自2013年起投入运行,有能力每年建设多达四艘油轮,并以前为石油、石油和化学运输运送了四艘油轮。
Baku Shipyard, operational since 2013, has a capacity to build up to four tankers annually and has delivered four tankers previously for oil, petroleum, and chemical transport.