在凯斯威克附近的B5289号山坡上对风暴德斯蒙德损坏的斜坡进行修理,从1月26日开始实行交通管制。
Repairs to Storm Desmond-damaged slopes on the B5289 near Keswick begin Jan. 26 with traffic controls.
在坎伯兰理事会的资助下,对Keswick附近Derwentwater海岸线的修理工作于1月26日恢复,对B5289号公路实行临时交通管制。
Repairs to the Derwentwater shoreline near Keswick, funded by Cumberland Council, resume January 26 with temporary traffic controls on the B5289.
Contractor Metcalfe's Plant Hire正在稳定2015年被德斯蒙暴风雨破坏的斜坡,使用石块和进口材料。
Contractor Metcalfe's Plant Hire is stabilizing a slope damaged by Storm Desmond in 2015, using stone and imported material.
第一阶段(截至2月20日)包括双向交通灯;第二阶段(从2月23日开始)要求重型机械从下午7时至上午7时关闭10次夜间。
Phase one, ending February 20, includes two-way traffic lights; phase two, starting February 23, requires 10 overnight closures from 7pm to 7am for heavy machinery.
工作旨在保护道路和自然景观。
The work aims to protect the road and natural landscape.
最新信息可通过公路热线或理事会网站查阅。
Updates are available via the Highways Hotline or council website.