中国出资在吉尔吉斯斯坦比什凯克的工厂于2025年12月28日开始运作, 每天将1千吨废物变成电力,
A Chinese-funded plant in Bishkek, Kyrgyzstan, began operations on Dec. 28, 2025, turning 1,000 tons of waste daily into electricity, cutting emissions, and creating jobs.
2025年12月28日在吉尔吉斯斯坦比什凯克启动了中国资助的废物变能源厂,每天将1 000吨废物转化为电力,每年发电1.46亿千瓦时,每年减少10万吨二氧化碳排放量。
A Chinese-funded waste-to-energy plant launched in Bishkek, Kyrgyzstan, on December 28, 2025, converting 1,000 tons of waste daily into electricity, generating 146 million kWh annually and cutting 100,000 tons of CO2 emissions yearly.
该项目由Hunan Junxin环境保护有限公司建造,于2024年8月开工,目的是改善废物管理,减少烟雾,促进电力供应和创造就业机会。
The project, built by Hunan Junxin Environmental Protection Co., Ltd., began construction in August 2024 and aims to improve waste management, reduce smog, boost electricity supply, and create jobs.
来自两国的200多名官员参加了仪式,领导人强调了环境和经济利益。