在几何动力的支持下,阿比阿州通过一个20亿奈拉项目,在近9年后恢复了33个社区的权力。
Abia State restored power to 33 communities after nearly 9 years via a N2 billion project with support from Geometric Power.
Abia州恢复了Ukwa西部33个社区的电力供应,在将近九年之后,通过由亚太和平协会领导的20亿新元项目,结束了长期停电。
Abia State restored electricity to 33 communities in Ukwa West after nearly nine years, ending a prolonged blackout through a N2 billion project led by ASOPADEC.
独立电力系统部分由几何电力有限公司提供的8亿美元供资,包括12台变压器、30个分站和一条42公里线。
The independent power system, funded partly by $800 million from Geometric Power Limited, includes 12 transformers, 30 substations, and a 42-kilometre line.
总督亚历克斯·奥蒂强调对低收入家庭的基础设施保护和支持,而官员确认进行计量,并不断努力防止破坏行为。
Governor Alex Otti emphasized infrastructure protection and support for low-income households, while officials confirmed metering and ongoing efforts to prevent vandalism.