Tillsonburg拒绝70M电池项目, 原因是安全性、离家近、收益不确定,
Tillsonburg rejected a $70M battery project due to safety, proximity to homes, and uncertain returns, despite promises of jobs and grid stability.
Tillsonburg镇议会拒绝在Van Norman创新公园实施一个耗资7 000万美元的电池储存项目,
Tillsonburg town council rejected a $70-million battery storage project at Van Norman Innovation Park, despite promises of grid stability, local jobs, and safer lithium-ion phosphate batteries.
30兆瓦设施旨在缓解高峰需求,但因靠近房屋、安全顾虑和回返情况不确定而面临反对。
The 30-megawatt facility aimed to ease peak demand but faced opposition over its proximity to homes, safety concerns, and uncertain returns.
安理会成员引用哈尔迪曼德县的一个类似项目作为警告性的例子。
Council members cited a similar project in Haldimand County as a cautionary example.
虽然将来有可能重新考虑,但没有计划立即采取行动。
While future reconsideration is possible, no immediate action is planned.