维多利亚州批准了两个主要可再生能源项目,即增强电网稳定和减少天然气使用。
Victoria approved two major renewable energy projects, boosting grid stability and reducing gas use.
维多利亚州批准了两个主要可再生项目:在Tramway Road的300MW/1 200MWh电池和在Meadow Creek储存250MW/1 000MWh的332MW太阳能发电厂,这是一个精简方案的一部分,加速了价值78亿澳元的22个项目。
Victoria approved two major renewable projects: a 300MW/1,200MWh battery at Tramway Road and a 332MW solar plant with 250MW/1,000MWh storage at Meadow Creek, part of a streamlined program accelerating 22 projects worth AU$7.8 billion.
到2025年,澳大利亚电网的电池部署量每年猛增150%,支持电网稳定和减少天然气使用。
Battery deployment in Australia’s grid surged 150% year-on-year by Q3 2025, supporting grid stability and reducing gas use.
由于电池成本下降和需要灵活、可靠的能源系统,向大型和分布式混合储存的转变势头正在增强。
A shift toward mixed-scale storage—both large and distributed—is gaining momentum, driven by falling battery costs and the need for flexible, reliable energy systems.