压倒性延迟风力项目因船舶问题而启动,但保留2025-2026年的时间表。
Dominion delays wind project start due to vessel issues but keeps 2025–2026 timeline.
由于需要对其9月抵达的符合《琼斯法案》的船只Charybdis进行工作,主宰能源推迟了弗吉尼亚沿海近海风力项目的风力涡轮机安装的开始时间。
Dominion Energy has delayed the start of wind turbine installation for its Coastal Virginia Offshore Wind project due to required work on its Jones Act-compliant vessel, Charybdis, which arrived in September.
这艘以7.15亿美元成本建造的472英尺船舶有200个未决问题,大多与电力系统有关,120多条问题得到解决。
The 472-foot ship, built at a $715 million cost, has 200 unresolved issues, mostly related to electrical systems, with over 120 resolved.
尽管出现拖延,但 " 主宰 " 公司预计将于2025年11月开始安装,到2026年Q1末开始安装第一电力。
Despite the delay, Dominion expects installation to begin in November 2025 and first power by late Q1 2026.
该项目已取得显著进展,包括完全安装单日装置和安置两个离岸分站。
The project has made significant progress, including full monopile installation and placement of two offshore substations.
由于关税和电网升级,项目总成本已增至112亿美元,但 " 主宰 " 公司维持了总体时间表,仍在按计划进行。
Total project costs have risen to $11.2 billion due to tariffs and grid upgrades, but Dominion maintains the overall timeline remains on track.