Silver X Mining的秘鲁项目计划6Moz/年银,439M NPV,启动费用82MM。
Silver X Mining's Peru project plans 6M oz/year silver, $439M NPV, with $82M startup cost.
Silver X Mining Corp.为秘鲁Nueva Recuperada的Nueva Recuperada银项目发布了初步经济评估,预测14年中年银等量生产量为600万盎司,税后净现值为4.39亿新元,累计现金流量为6.06亿美元。
Silver X Mining Corp. has released a Preliminary Economic Assessment for its Nueva Recuperada silver project in Peru, projecting 6 million ounces of annual silver equivalent production over a 14-year life, with a $439 million after-tax NPV and $606 million in cumulative cash flow.
该项目每天有3 000吨容量和2个碾磨设施,其LOM现金费用为每盎司11.80美元,AISC费用为15.80美元,得到8 200万美元的初始资本支出的支持。
The project, with a 3,000-tonne-per-day capacity and two milling facilities, has LOM cash costs of $11.80 per ounce and AISC of $15.80, backed by an $82 million initial capital outlay.
PEA包括经济尚不可行的推断资源,属于初步性质。
The PEA includes inferred resources not yet economically viable and is preliminary in nature.
该公司最近完成了一笔超额融资,用于预先开发并重新启动普拉塔采矿股。
The company recently completed an oversubscribed financing to advance development and restart the Plata Mining Unit.