Stowe Township考虑重新划定一个72英亩的数据中心场地,
Stowe Township considers rezoning a 72-acre site for a data center backed by a $6M state grant, sparking debate over development and transparency.
Stowwe镇专员正在考虑SunCap Industries提出的一项提案,将一个72英亩的前铁路车厂址重新划为数据中心,此举可以刺激经济发展,并与600万美元的州棕色地带再开发赠款相一致。
Stowe Township commissioners are considering a proposal from SunCap Industries to rezone a 72-acre former railcar plant site for a data center, a move that could spur economic development and align with a $6 million state brownfield redevelopment grant.
该项目仍处于早期阶段,引起了居民和官员对基础设施、电力使用和透明度的关切,不过专员们强调,在作出最后决定之前,需要社区投入和收集事实。
The project, still in early stages, has raised concerns among residents and officials about infrastructure, power usage, and transparency, though commissioners stress the need for community input and fact-gathering before a final decision.
投票前将发布公共公告。
A public notice will be issued ahead of a vote.