Auric Mining公司提前三天从西澳大利亚州的Munda项目开始加工黄金矿石,目标是在11月获得第一批黄金收入。
Auric Mining began processing gold ore from its Munda project in Western Australia three days early, aiming for first gold revenue in November.
Auric Mining公司从三天前在西澳大利亚的Munda项目开始加工黄金矿石,第一批60,000吨高等级矿石现在正在Kalgoorlie的Lakewood Mills被碾磨。
Auric Mining has started processing gold ore from its Munda project in Western Australia three days early, with the first 60,000-tonne batch of high-grade ore now being milled at Kalgoorlie’s Lakewood Mill.
该公司预计将在11月创造第一笔黄金收入,预测最高为125 000吨1.8克/吨的6 100盎司黄金收入,初期全部维持费用为每盎司2 635美元。
The company expects to generate its first gold revenue in November, forecasting 6,100 ounces from up to 125,000 tonnes grading 1.8 g/t, with an initial all-in sustaining cost of $2,635 per ounce.
黄金价格高于每盎司6 300美元,提高了预期回报率。
Elevated gold prices above $6,300 per ounce are boosting projected returns.
及早启动提供关键现金,为进一步勘探和开发提供资金。
The early start provides critical cash to fund further exploration and development.
起始坑使用干租赁车队和当地支持,其特点是浅浅、免费挖掘的矿石,带宽比率低,具有成本效益。
The starter pit, using a dry-hire fleet and local support, features shallow, free-digging ore with a low strip ratio, enabling cost efficiency.
该运动的数据将为大型主要矿坑的计划提供信息,矿坑的储量为3.65万吨,每吨1.23克,可能达到189 000盎司。
Data from the campaign will inform plans for a larger main pit, where the deposit holds 3.65 million tonnes at 1.23 g/t, with potential to reach 189,000 ounces.
一项2023年的研究已经显示出强大的潜力,现在由于目前的市场条件而扩大。
A 2023 study had already shown strong potential, now amplified by current market conditions.