Peel NRE plans to demolish remaining Fiddlers Ferry power station structures by 2027, redeveloping the site into a mixed-use area with homes, jobs, and a battery storage system.
Peel NRE 已提交规划申请,拆除退役的 Fiddlers Ferry 发电站的最终结构,包括四座冷却塔、烟囱、涡轮机房和锅炉房,预计将于 2025 年底开始,并于 2027 年底完成。
Peel NRE has submitted a planning application to demolish the final structures at the decommissioned Fiddlers Ferry power station, including four cooling towers, chimney, turbine hall, and boiler house, with work expected to start by end of 2025 and finish by late 2027.
该网站于2020年关闭,将重新开发成为一个混合使用区,有多达860套住房(30%可负担)和101公顷就业空间,可能创造845个就业机会。
The site, closed in 2020, will be redeveloped into a mixed-use area with up to 860 homes—30% affordable—and 101 hectares of employment space, potentially creating 845 jobs.
该项目包括新的运输连接、公共设施以及拟议的150兆瓦电池储存系统。
The project includes new transport links, public amenities, and a proposed 150MW battery storage system.
在2023年四座冷却塔倒塌和现场持续补救后进行拆除。
Demolition follows the 2023 collapse of four cooling towers and ongoing site remediation.