印度尼西亚开始在西爪哇建造一座92兆瓦的浮动太阳能发电厂,目标是2026年11月的运营。
Indonesia begins constructing a 92-megawatt floating solar plant in West Java, targeting November 2026 operation.
印尼已开始在西爪哇的Saguling水库建造一座92兆瓦的浮峰式太阳能发电厂,
Indonesia has started building a 92-megawatt-peak floating solar plant on West Java’s Saguling reservoir, led by state utility PLN.
预计2026年11月开始运作,每年将产生130多千兆瓦时,每年减少104,000吨碳排放量。
Expected to begin operations in November 2026, it will generate over 130 gigawatt-hours annually and cut 104,000 tons of carbon emissions yearly.
该项目支持印度尼西亚的目标,即到2034年增加42.6千兆瓦的可再生能源,太阳能占17.1千兆瓦。
The project supports Indonesia’s goal to add 42.6 gigawatts of renewable energy by 2034, with solar accounting for 17.1 gigawatts.
在此之前,尼泊尔人民进步党和阿联酋的马斯达尔公司在该区域发起了一项浮动太阳能倡议。
It follows a prior floating solar initiative in the region by PLN and UAE-based Masdar.
新工厂的投资没有披露, 但官员称这是国家清洁能源转变的一大步。
The investment for the new plant is not disclosed, but officials call it a major step in the nation’s clean energy shift.