乍得启动了第一座主要太阳能发电厂,促进清洁能源和减少排放。
Chad launched its first major solar plant, boosting clean energy and cutting emissions.
2025年9月28日, 位于恩贾梅纳的50兆瓦Nour Chad设施(50 MW Noor Chad)为约274 000个家庭提供清洁能源,
Abu Dhabi-based Global South Utilities inaugurated Chad’s first large-scale solar plant, the 50 MW Noor Chad facility in N’Djamena, on September 28, 2025, providing clean energy to about 274,000 homes.
该项目在创纪录的时间内完成,包括5兆瓦电池储存系统、81 000个太阳能电池板和158个转换器,建造时安全工作时数超过350 000小时。
The project, completed in record time, includes a 5 MWh battery storage system, 81,000 solar panels, and 158 inverters, built with over 350,000 safe work-hours.
预计它将在其整个生命周期内减少136万吨以上的二氧化碳排放量,并减少对进口柴油的依赖。
It is expected to cut over 1.36 million tonnes of CO2 emissions over its lifetime and reduce reliance on imported diesel.
开发商和运营商GSU称这是乍得迈向可持续能源的变革性步骤。
GSU, the developer and operator, called it a transformative step toward sustainable energy in Chad.
来自乍得和阿联酋的高级官员出席了开幕式,强调阿联酋致力于全球南部的气候友好发展和经济伙伴关系。
The inauguration was attended by high-level officials from Chad and the UAE, highlighting the UAE’s commitment to climate-friendly development and economic partnerships in the Global South.