Mumbai's bullet train station at Bandra Kurla Complex is 84% complete, with deep excavation nearing finish.
84%的挖掘工作已经完成,用于孟买Bandra Kurla Complex的地下弹道列车站,这是孟买-艾哈迈德巴德高频铁路走廊上唯一的此类站。
84% of excavation is complete for Mumbai's underground bullet train station at Bandra Kurla Complex, the only such station on the Mumbai-Ahmedabad High-Speed Rail corridor.
该场址挖掘深度为32.5米,将设六个平台、三层楼以及连接Metro Line 2B和道路网络。
The site, dug to a depth of 32.5 meters, will feature six platforms, three floors, and connections to Metro Line 2B and road networks.
这个项目由日本支助,涉及18.7万立方米土土工程,已完成15.7万立方米土工程。
The project, supported by Japan, involves 18.7 lakh cubic meters of earthwork, with 15.7 lakh already completed.
完工后,预计走廊将在两个城市之间提供更快、更安全和更可靠的旅行。
Upon completion, the corridor is expected to offer faster, safer, and more reliable travel between the two cities.