罗马尼亚向Iernute发电厂的Duro Felguera开火,原因是破产、拖延项目。
Romania fires Duro Felguera from Iernut power plant over insolvency, stalling project.
罗马尼亚能源部长以该公司的破产和法律问题为由,终止了与Duro Felguera关于几乎完整的Iernut发电厂的合同。
Romania's Energy Minister terminated the contract with Duro Felguera over the nearly complete Iernut power plant, citing the company's insolvency and legal issues.
该项目已停顿多年,搬迁为新承包商提供了可能性。
The project has been stalled for years, and the move opens the possibility of a new contractor.
与此同时,罗马尼亚的工资增长速度超过了通货膨胀,实际工资下降,预测还会进一步下降,可能导致2025-2026年冻结公共工资和养老金。
Meanwhile, wage growth in Romania has been outpaced by inflation, with real wages declining and forecasts predicting further erosion, potentially leading to frozen public wages and pensions in 2025–2026.
该国在面临经济挑战以及最近欧盟国家批准对能源密集型公司提供5.78亿欧元援助的情况下,也面临着消极的信贷前景。
The country also faces a negative credit outlook amid economic challenges and a recent €578 million EU state aid approval for energy-intensive firms.