Weirton废水处理厂的扩建旨在将容量增加一倍,现已完成47.9%,将在2026年7月完成。
Weirton's wastewater plant expansion, aiming to double capacity, is 47.9% complete, on track for July 2026.
授予Triton建筑公司3 700万美元的Weirton废水处理厂扩建项目进展顺利,目前已完成47.9%。
The Weirton wastewater treatment plant expansion project, awarded to Triton Construction for $37 million, is progressing well, currently at 47.9% completion.
目标是到2026年7月将工厂每天的生产能力翻一番,从400万加仑增加到800万加仑。
The goal is to double the plant's capacity from 4 million to 8 million gallons per day by July 2026.
已计划临时停工,但已制定了应急措施。
Temporary shutdowns are planned but with contingency measures in place.
扩展的目的是适应一家大型制造公司的潜在增长。
The expansion aims to accommodate potential growth from a large manufacturing company.