至2025年3月15日是印度法院批准清真寺拆除未经授权的地板的期限。
Indian court grants deadline until March 15, 2025, for mosque to remove unauthorized floors.
至2025年3月15日, Shimla市政专员已授权Sanjauli清真寺委员会拆除该清真寺三层未经授权的楼层。
The Shimla Municipal Commissioner has given the Sanjauli Mosque Committee until March 15, 2025, to demolish the mosque's three unauthorized floors.
委员会最初下令在8周内拆除,但报告说,50%的工作已经完成。
Initially ordered to be demolished within eight weeks, the committee reported that 50% of the work is done.
法院已安排在3月15日举行下一次听讯,届时委员会和喜马恰尔邦宗教基金委员会必须提供状况报告和相关文件。
The court has scheduled the next hearing for March 15, when the committee and the Himachal Pradesh Waqf Board must provide a status report and relevant documents.