作为政府加强能源储存系统计划的一部分,CEA核准印度600兆瓦的上因德拉瓦蒂和2000兆瓦的沙拉瓦提水泵储存厂。 CEA approves 600 MW Upper Indravati and 2000 MW Sharavathy Hydro Pumped Storage Plants in India, as part of a government plan to enhance energy storage systems.
中央电力局 (CEA) 已批准印度的两家水电抽水蓄能电站 (PSP),分别是 OHPC Ltd 在奥里萨邦的 600 MW Upper Indravati 和 KPCL 在卡纳塔克邦的 2000 MW Sharavathy。 The Central Electricity Authority (CEA) has granted approval to two Hydro Pumped Storage Plants (PSPs) in India, the 600 MW Upper Indravati in Odisha by OHPC Ltd and the 2000 MW Sharavathy in Karnataka by KPCL. 这些项目是政府通过发展能源储存系统,特别是PSP系统,加强能源储存系统和确保能源安全努力的一部分,预计到2031-32年将安装74个GW。 These projects are part of the government's effort to enhance energy storage systems and ensure energy security by developing Energy Storage Systems, particularly PSPs, with a projected 74 GW installed capacity by 2031-32. 能源中心简化了编写详细项目报告的程序,并缩短了同意加快开发这些能源项目所需的时间。 The CEA has simplified the process for preparing Detailed Project Reports (DPRs) and reduced the time required for concurrence to expedite the development of these energy projects.