中铁二十局集团完成马拉维马尔卡-孟加拉铁路最长桥梁的修建,该桥梁是连接赞比亚和莫桑比克的 72 公里修复项目的一部分。 China Railway 20th Bureau Group completes the longest bridge on Malawi's Marka-Bangula railway as part of a 72-km rehabilitation project, connecting Zambia to Mozambique'
中国中铁二十局集团有限公司(CR20)已完成马拉维马尔卡-孟加拉铁路上最长的桥梁,这是 72 公里铁路修复项目的一部分。 Chinese company China Railway 20th Bureau Group (CR20) has completed the longest bridge on the Marka-Bangula railway in Malawi as part of a 72-km railway rehabilitation project. 这根长20.6米、重38吨的预制T梁被放置在桥墩上。 The 20.6-meter precast T-beam, weighing 38 metric tons, was placed on a pier. 该项目预计2025年10月完工,旨在促进赞比亚与莫桑比克贝拉港之间的客运和货物交流,并为南部非洲国家打造重要的海上通道。 The project, expected to be completed by October 2025, aims to facilitate the exchange of passengers and goods between Zambia and the port of Beira, Mozambique, and create a vital sea passage for southern African countries.