BHEL 从 Adani Power 获得了位于恰蒂斯加尔邦 1,600 兆瓦 Raigarh 二期热电厂的 400 亿卢比订单。 BHEL secures a Rs 4,000 crore order from Adani Power for the 1,600 MW Raigarh Phase-II Thermal Power Plant in Chhattisgarh.
BHEL 从 Adani Power 获得了位于恰蒂斯加尔邦 1,600 兆瓦 Raigarh 二期热电厂的 400 亿卢比订单。 BHEL secures a Rs 4,000 crore order from Adani Power for the 1,600 MW Raigarh Phase-II Thermmal Power Plant in Chhattisgarh. 该订单包括为基于超临界技术的 2x800 MW 电力项目提供设备以及监督安装和调试。 The order includes the supply of equipment and supervision of erection and commissioning for a 2x800 MW power project based on supercritical technology. BHEL 的 Trichy 和 Haridwar 工厂将生产锅炉和涡轮发电机,预计 31 个月内供应 1 号机组,35 个月内供应 2 号机组。 BHEL's Trichy and Haridwar plants will manufacture the boiler and Turbine Generator, with the supply of Unit-1 expected in 31 months and Unit-2 in 35 months.